Monday, August 1, 2011

My recent projects. Multifunctional shopping complex

The objective of this project was creation of an engineering solution for the multifunctional shopping complex, which the customer planned to build in the area of crossing of four lively highways connecting the densely populated district with the centre of city and with exit roads to the suburbs. The shopping complex was to be placed near the underground station with a high passenger traffic flow and should have direct passenger communication. The complex should have a multistory underground car park, an overground zone for shops and offices with total square of more than 47500 sq.m. (including 21500 sq.m. for lease). At the moment of the beginning of designing, transport situation was complicated in the area of object placement, and the traffic organization scheme needed to be fully revised.





The work aimed at project creation of an object with a parking and office area, which would fall in with the existing building development and have direct communication with the underground station hall.



Background

At the same time, a traffic management scheme had to be changed to increase traffic capacity in this transport node. The designing bureau was a general contractor, which took a responsibility for development of the architectural and construction part of the project. This company hired me especially to create a new traffic management scheme and to design the technological nodes of the parking and the underground zone. The decision was based on my previous experience in development and construction of the cast-in-place and precast concrete reservoirs, where the modern methods of buried walls construction were used, and also considering my specialized education in traffic management field.




On the one hand, my part of the work consisted in searching for original designs of the underground part of the complex, which had to be attached to the overground part; on the other hand I had to integrate the parking in a new scheme of automobiles and pedestrians traffic management. Thus, my obligations included: prototype analysis and engineering design of the underground parking with 400 places capacity for the multifunctional complex; selection of necessary methods to build the underground part, considering proximity of a railway station; adoption of a traffic scheme in the construction area to new conditions during construction (a temporary scheme) and its posterior modernization for traffic flow optimization after the construction finished; author’s supervision during construction for prompt solution of arising problems and design choices development.




All necessary strength calculations and calculation of elements and underground structures, rough construction estimate, general drawings of the building and original (non-typical) technical solutions I made by myself. Drawings of typical nodes and all standard calculations were made by general contractor’s specialists. Also I provided the required calculation to substantiate necessity of changes in the traffic management scheme for approvement in the supervisory bodies. Some corrections were added by the specialists of the Traffic Management Committee. 

Solution

At the first stage, before design starts, it was necessary to select a proper traffic management scheme and choose a certain place for multifunctional centre placement on the proposed site (master plan development). I have analysed transport density and traffic capacity of the existing roads and crossings in the construction area and have drawn a conclusion that the best traffic management scheme here will be a circular (roundabout) traffic scheme.




Hence, the task was to place the parking within the bounds of this ring, providing access for the pedestrians to the main building from the underground station hall as well as from the overground crosswalks. Motor vehicles should enter the parking from the ring-road as well, and it was necessary to minimize obstacles for transit transport caused by route change and speed down of the vehicles entering the parking. In this case I used my knowledge of traffic management acquired during my study at the State University of Architecture & Civil Engineering at the Road Traffic Management Department. Firstly, I have developed a temporary traffic scheme for the whole period of construction. After that, I developed a perspective scheme of road node (road interchange) reconstruction and a permanent traffic management scheme after termination of the construction, considering traffic intensity increase.




After the position of the shopping centre had been determined, and it had been decided that the complex should have a cylindrical form, I made comparison of different types of underground parkings, which could be used under the given conditions, on correlation between cost and total area to square and number of car spaces. During the analysis, all existing garages were divided in two groups – with inclined or spiral ways for entry/exit and with lifts. The garages with inclined floors could not be used here, because they imply primarily a rectangular form of building and may cause holdups under restricted conditions in rush-hours. The garages with spiral floors mean construction of separate descents, which are expensive in underground construction and restrict the number of additional parking places. The garages with lifts are very expensive and decrease traffic capacity, as queues of vehicles will stand on the ring in wait for entry.




So, I decided to adopt my invention patented in Russia (RU 2129197) - “Multilevel garage complex“, as in this case there is an opportunity to use space for parking to the maximum, it is simple and cheap in underground construction, it is easily adjusted to the ring traffic scheme.



This is a constructive solution, where building consists of two coaxial (one inside another) vertical caissons. Between caissons walls on the floors there are separate parking places and access ways to them – two  symmetrical (left and right) spiral roads, leaning on external (or internal) building walls from the one side, and on the supporting reinforced concrete pillars from the other side. One road passes along the parking spaces at external caisson walls, and  the other - along the parking spaces at internal caisson walls. Roundabout inside the garage is realized only in one direction, which increases traffic safety. There are common traffic sections (areas) in the places of junction of the symmetrical spiral roads to each other (two junctions per a circle, as the internal and external spirals differ: one is left and the other is right). These sections serve for change of direction from ascent to descent and vice versa (if necessity arises).

This solution also allows to use the central part of the underground garage for additional parking as well as for rented spaces.




To integrate the underground parking into the existing ring traffic, two semicircle roads with a single path go from the underground building to the ring area: one for entry (descent) to the garage and the other for exit (ascent) from it. A top mark of the underground part of external walls coincides with a lower mark of concrete road surface on ring traffic area, and overall depth of the garage (18 m) allowed to develop four levels of parking places to achieve the required capacity.

In order to prevent crossing of the main stream of visitors with traffic flow, I have designed a pedestrian subway sizes 12mx4m of specified width through the parking form the underground station hall and another subway nearby.




Also I have provided recommendations for further calculation of ventilation and air-conditioning systems, storm drainage and groundwater drainage systems.

As generally construction of the parking was unconventional, during the development, besides the AutoCAD/Revit program, I also used the APM Civil Engineering automated calculation and construction design system and the APM Structure3D module for project and checking calculation of reinforced concrete constructions, creating the stress map, strength and dynamic analysis of parts by FEM. The rest of typical nodes and overground part were calculated by specialists of the project contractor company.




Relying on the geological engineering survey data in the construction site obtained from a company-builder of underground stations, I decided to use a caisson method as the cheapest for construction of external walls.

After that, I made calculation of rock steadiness, chose a type of shore for the caisson, and also determined main and additional loads on the shaft collar shore from the buildings and structures surrounding the construction site on surface.




Thereafter, I elaborated a detailed work performance plan and gave a complex assessment of probable consequences of construction for the neighbouring buildings. Here I used my previous experience in buried structures calculation obtained during designing of drinking water storage and filtering reservoirs.

After designing and project approvement had been finished, I began to provide author’s supervision over building erection. Special attention was given to caisson sinking (external walls) and prevention of sinking irregularity (lateral inclination), providing regular geodesic control.



After the external caisson wall had been built, I provided control over reinforcing and concrete works during erection of monolithic internal cylindrical walls, pillars, floors - symmetrical spiral roads. To erect the internal cylindrical wall, I have developed a method of using self-propelled plants of horizontally sliding formwork (a rail carriage with pillars and a winch for shield lifting), which would move on a round rail way  for concreting of internal caisson walls. This method is economically rational for large diameter of ring, as is in our case.


 

The floors have been built using reusable formwork systems produced by “Peri” (Germany), as in this case every formwork set was individual for each part of the building. That is why I have projected them in RUMBA, a computer program for formwork selection and three-dimensional arrangement, and then they were assembled and mounted at the site.

  

Upon construction termination the new circular traffic management scheme proved its efficiency, as measurements have shown increase of intersection capacity in general. This allowed to avoid holdups in rush hours and queues at node access way, despite the fact that density has increased by 2.5 times in the result of construction of such building.



Summary

Successful accomplishment of construction has shown that the goal to integrate the multifunctional complex with the underground parking into the traffic circle had been achieved. Also underground space under a high-density area has been used efficiently, and the traffic management scheme has been improved. These results were produced due to the deep analysis of collected data on transport unit and application of relevant methodologies related to traffic capacity computation and traffic volume planning. My role in the project consisted in designing and full engineer’s development of the underground part of the object. I used my inventions, adapted and used the modern methods of underground construction. As a result, I have acquired additional knowledge of underground construction, which I used during designing as well as control over building erection.

No comments:

Post a Comment